Turbine Specific Crane (TSC)  Transport overview and assembly process 

   

Transport Overview for TSC with crane foundation   prepared at installation site 

 

 

   

Add‐on transports if crawler crane base is used as  TSC foundation 

 

   

Add‐on transports if mobile crane base is used as  TSC foundation 

 

   

Transportation of TSC to installation site 

 

   

Install TSC crane base including 3m lattice section   on pre‐prepared support foundation 

 

   

Lift / slide crane operator cabin into position  (Cabin inside crane structure to ensure max transport dim.) 

 

   

Connect both crane booms to main crane base  and install derrick and crane hook wires 

 

   

Up‐end and Install first TSC 25m lattice tower   section using the lower crane winch 

 

   

Assemble counterweight setup on the ground 

 

   

Climb up to ensure clearance, rotate TSC crane   and connect to counterweight system 

 

   

Use spur gear and rack system to climb the TSC   crane to the top of the lattice tower section 

 

   

Lift and install 2nd lattice tower section 

 

   

Lift and install 3rd lattice tower section 

 

   

Lift and install 4th lattice tower section 

 

   

Lift and install 5th lattice tower section 

 

   

TSC ready for wind turbine installation activities 

 

   

The 2 crane hook positions allow up‐ending of   crane lattice tower section without support crane assistance 

   

Main crane setup climbing down for re‐location of  crane internally on installation site 

 

   

TSC crane re‐locating using ...