Turbine Specific Crane (TSC) Transport overview and assembly process Disclosure Number: IPCOM000250400D
Publication Date: 2017-Jul-11
Document File: 20 page(s) / 3M

Publishing Venue

The Prior Art Database

This text was extracted from a PDF file.
This is the abbreviated version, containing approximately 99% of the total text.

Turbine Specific Crane (TSC)  Transport overview and assembly process 


Transport Overview for TSC with crane foundation   prepared at installation site 




Add‐on transports if crawler crane base is used as  TSC foundation 



Add‐on transports if mobile crane base is used as  TSC foundation 



Transportation of TSC to installation site 



Install TSC crane base including 3m lattice section   on pre‐prepared support foundation 



Lift / slide crane operator cabin into position  (Cabin inside crane structure to ensure max transport dim.) 



Connect both crane booms to main crane base  and install derrick and crane hook wires 



Up‐end and Install first TSC 25m lattice tower   section using the lower crane winch 



Assemble counterweight setup on the ground 



Climb up to ensure clearance, rotate TSC crane   and connect to counterweight system 



Use spur gear and rack system to climb the TSC   crane to the top of the lattice tower section 



Lift and install 2nd lattice tower section 



Lift and install 3rd lattice tower section 



Lift and install 4th lattice tower section 



Lift and install 5th lattice tower section 



TSC ready for wind turbine installation activities 



The 2 crane hook positions allow up‐ending of   crane lattice tower section without support crane assistance 


Main crane setup climbing down for re‐location of  crane internally on installation site 



TSC crane re‐locating using ...